Rudbar Lorestan Dam
| Rudbar Lorestan Dam | |
|---|---|
|   Location of Rudbar Lorestan Dam in Iran | |
| Country | Iran | 
| Coordinates | 32°54′14″N 49°41′03″E / 32.90389°N 49.68417°E | 
| Purpose | Power | 
| Status | operational | 
| Construction began | 2003 | 
| Opening date | 2016 | 
| Dam and spillways | |
| Type of dam | Gravity, roller-compacted concrete | 
| Impounds | Rudbar River | 
| Height (foundation) | 155 m (509 ft) | 
| Height (thalweg) | 158 m (518 ft) | 
| Length | 185 m (607 ft) | 
| Elevation at crest | 1,765 m (5,791 ft) | 
| Width (crest) | 15 m (49 ft) | 
| Dam volume | 4,596,000 m3 (6,011,341 cu yd) | 
| Spillways | 2 | 
| Spillway type | Tunnel with flip-buckets | 
| Spillway capacity | 3,342 m3/s (118,022 cu ft/s) | 
| Reservoir | |
| Total capacity | 228,000,000 m3 (184,843 acre⋅ft) | 
| Active capacity | 124,000,000 m3 (100,528 acre⋅ft) | 
| Surface area | 4.11 km2 (2 sq mi) | 
| Maximum length | 20 km (12 mi) | 
| Maximum width | 20 m (66 ft) | 
| Power Station | |
| Commission date | 2017 | 
| Turbines | 2 x 225 MW Francis-type | 
| Installed capacity | 450 MW | 
| Annual generation | 986 GWh (est.)[1] | 
Rudbar Lorestan Dam (Persian: سد رودبار لرستان) is a hydroelectric dam on the Rudbar River, a tributary of the Dez River, in Iran's Lorestan Province with an installed electricity generating capability of 450 MW. It was scheduled to become operational in 2013.[2] Finally, the dam was completed on September 15, 2016.[3] The hydroelectric plant consisting of two 225-MW vertical Francis turbine-generator units has begun operating on May 31, 2017.[4]
See also
References
- ^ "Rudbar Lorestan Technical Information". IWPCO. Retrieved 20 October 2012.
- ^ "Home - Iran Water and Power Resources Development Co". en.iwpco.ir. Archived from the original on 2008-12-05.
- ^ "Iran Rudbar Lorestan hydropower dam undertaken by CGGC completed".
- ^ "Your Dedicated Source of Hydropower News".

Wikimedia Commons has media related to Rudbar Dam.